  • Slot dozing, which consists of dozing repeatedly in the same tracks, will increase production. The deeper the slot, the greater the increase in production. Obviously this will disrupt the surface of the pile; however it does provide maximum production. Edition 44 29-3 Production Factors Stockpile Coal Handling Estimating Hourly Production Slot.
  • Start dozing from the front of the dozing zone. As seen from the picture, if working on level ground, dozing should start at the front. This reduces the distance that material must be pushed. The dozers blade is also always full by using a downward grade.
Figure 11-26.-Side-by-side dozing.Figure 11-27.-Slot dozing.Side-by-side dozing (fig. 11-26) and slot dozing(fig. 11-27) maximize the amount of earth drifted byreducing or preventing spillage around the outer edgesof the blade.SIDE-BY-SIDE DOZING.— In side-by-sidedozing, two dozers work abreast with blade edges asclose together as possible, preventing spillage aroundone blade edge on each dozer. Side-by-side dozingrequires time-consuming maneuvering of the dozers;therefore, it is impractical for hauls of less than 50 feetand more than 300 feet.SLOT DOZING.— Slot dozing is done by firstbuilding a pair of windrows with the spillage of severalpasses. As shown in figure 11-27, the windrows serveas barriers to prevent spillage around the dozer bladeends. Under favorable conditions, slot dozing canincrease production up to 50 percent.11-14

Old Antique Dozers Moving Dirt

According to the Caterpillar Performance Handbook edition 36, section 1, page 42, slot dozing has a 1.20 correction factor when calculating dozer production, whereas a poor operator has a.60 correction factor. I just went over the jist of it, there are different conditions that will effect your outcome.